The transition process comprises the following key steps:
1. Submission of transition request by the project participants to the secretariat (by 31 December 2023 for CDM project activity or PoA other than a CDM A/R project activity or CDM A/R PoA and CPAs therein; by 31 December 2025 for CDM A/R project activity or CDM A/R PoA and the CPAs therein);
2. Global stakeholder consultation (for 28 days);
3. Approval of transition by the host Party to the secretariat (by 30 June 2026);
4. Submission of additional documentation to the secretariat:
(a) Addendum to the registered CDM PDD, or PoA-DD and CPA-DDs, to demonstrate compliance with the requirements for transition, by the project participants, if the activities continue to apply the currently applied CDM methodologies (by 31 December 2026); or
(b) Revised PDD, or PoA-DD and CPA-DDs, and validation report by the designated operational entity, if the activities switch to Article 6.4 mechanism methodologies (within 1 year of publication of the host Party approval or within 1 year after the applicable methodology becomes available, whichever is later);
5. Payment of transition fee (activities hosted in non LDC-SIDs are waived);
6. Completeness check by the secretariat;
7. Substantive check by the secretariat;
8. Possible review of the transition request by the Supervisory Body;
9. Approval or rejection of transition by the Supervisory Body;
10. If transition is approved, deregistration from the CDM.