20 February 1997
ENGLISH ONLY
UNITED NATIONS FRAMEWORK CONVENTION ON CLIMATE CHANGE
SUBSIDIARY BODY FOR IMPLEMENTATION
Fifth Session
Bonn, 25-28 February 1997
Item 4 (b) of the provisional agenda
The Conference of the Parties, at its second session, by its
decision 10/CP.2 requested the Convention secretariat to make
available to the Subsidiary Body for Implementation (SBI), at each of
its sessions, details of the financial support made available to
Parties not included in Annex I to the Convention from the interim
operating entity of the financial mechanism for the preparation of
their initial communications, including projects in this regard
proposed by each Party, the funding decisions and the date and amount
of funds made available to the Party
(FCCC/CP/1996/15/Add.1).
The attached table* contains information provided by the Secretariat of the
Global Environment Facility (GEF) in response to that
decision.
Funds are considered available to the Parties from the date when
the project documents are signed by the Parties and the implementing
agencies. Such dates are listed in the column entitled "Date of
Project Document Signature" in this table. In order to make it
possible for Parties to start work without delay on enabling activity
projects approved under expedited procedures, it was decided in July
1996 that 15 percent of the total funds for such projects may be made
available to Parties as soon as the projects are approved by the
Chairman and Chief Executive Officer of the GEF, which would be
before the date on which the project documents are
signed.
In accordance with the procedure for miscellaneous documents, the
table is reproduced in the language in which it was received and
without formal editing.
FCCC/SBI/1997/MISC.1
GE.97-
___________________
* In order to make these submissions available on electronic systems, including the World Wide Web, these contributions have been electronically scanned and/or retyped. The secretariat has made every effort to ensure the correct reproduction of the texts as submitted.
|
|
|
|
|
|
|
| ||||||
| ||||||
|
|
|
|
|
|
|
Bangladesh, China, DPRK, India, Indonesia, Mongolia, Myanmar, Pakistan, Philippines, Thailand & Vietnam |
|
Asia Least-cost GHG Abatement Strategy (ALGAS) |
12/91 |
08/18/94 |
9.50 |
Project to be completed by June 1997. Three major regional workshops and national workshops held for individual countries. Mitigation options identification workshop scheduled for Feb. 1997 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Ghana, Kenya, Mali and Zimbabwe |
UNDP |
Building capacity in Sub-Saharan Africa to respond to the UNFCCC |
12/92 |
08/16/95 |
2.00 |
Project under execution. Second Project Steering Committee meeting scheduled for early 1997. |
India |
UNDP |
Cost-Effective Options for Limiting GHG emissions |
05/93 |
|
1.50 |
Project document under preparation by nationally designated organization |
|
Country |
Implementing Agency |
Project Title |
Date of Country Endorsement |
Date of GEF Council Approval |
Date of Project Document Signature |
GEF Allocation |
Comments |
| |||||||
|
|
|
|
|
|
|
|
Antigua & Barbuda, Bahamas, Barbados, Belize, Dominica, Grenada, Jamaica, St. Kitts and Nevis, St. Lucia, Trinidad and Tobago |
World Bank |
Regional (CARICOM) Planning for Adaptation to Climate Change |
N/A Multi-Country Project |
|
|
|
|
|
|
|
|
|
|
|
|
Antigua & Barbuda, Cameroon, Estonia,
Pakistan |
UNEP |
Country Studies on Climate Change Impacts and Adaptation Assessment |
N/A Multi-Country Project |
|
|
2.00 |
|
Argentina |
UNDP |
Country Study on Climate Change |
12/07/94 |
01/17/96 |
02/16/96 |
1.00 |
Project initiation workshop held on 07/03/96-07/04/96. |
|
|
|
|
|
|
|
--- |
Armenia |
UNDP |
Country Study on Climate Change |
03/31/95 |
12/15/95 |
05/07/96 |
0.35 |
|
|
|
|
|
|
|
|
|
Cook Islands, Cuba, Ecuador, Fiji, Kiribati, Marshall Islands, Nauru, Paraguay, Peru, Senegal, Solomon Islands, Tuvalu, Vanuatu & W. Samoa |
|
|
|
|
|
|
Three Regional Training Workshops to be held in the second and third quarter of 1997. |
|
|
|
|
|
|
|
|
Bhutan |
UNDP |
Enabling Activity |
01/30/96 |
07/26/96 |
08/15/96 |
0.30 |
|
Botswana Brazil |
UNDP UNDP |
Enabling Botswana to fulfill its commitments to the
UNFCCC Enabling Braz il to fulfill its commitments to the UNFCCC |
11/18/94 08/31/95 |
08/14/96 07/14/96 |
09/05/96 08/01/96 |
0.35 1.50 |
|
|
|
|
|
|
|
|
|
Cook Islands, Fiji, Kiribati, Marshall Islands, Fed.
States of Micronesia, Nauru, Solomon Islands, Tuvalu,
Vanuatu & W. Samoa Costa Rica |
UNDP UNDP |
Pacific Island Climate Change Assistance Project
(PICCAP) Building National Technical Capacity to Develop Options for GHG emissions reductions and carbon sinks enhancement |
N/A Multi-Country Project 12/08/94 |
--- 06/07/96 |
--- 08/07/96 |
2.44 0.47 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Project initiation workshop held on 09/29/96. |
Lao People's Democratic Republic |
|
National GHG Inventory Project |
07/19/95 |
07/29/96 |
10/30/96 |
0.31 |
|
|
|
|
|
|
|
|
Project work plan under preparation |
Malaysia |
UNDP |
National GHG Inventory and Response to the UNFCCC |
04/01/95 |
09/13/96 |
10/30/96 |
0.47 |
|
|
|
|
|
|
|
|
Project document signature anticipated Jan. 1997. |
Papua New Guinea |
UNDP |
Enabling Activity |
01/17/96 |
12/30/96 |
--- |
0.35 |
Subcontracts for project activities under preparation |
Tunisia |
UNDP |
National Strategy and Action Plans for emission reduction
and communications under the UNFCCC. |
02/03/95 |
08/14/96 |
09/06/96 |
0.57 |
Project document signature anticipated in Jan. 1997 |
Uruguay |
UNDP |
Institutional strengthening and enabling activities to comply with the UNFCCC |
11/25/94 |
11/13/95 |
12/18/96 |
0.70 |
|
Uzbekistan |
UNDP |
Country Study on Climate Change
|
08/07/95 |
01/02/97 |
|
0.33 |
|
Zaire |
UNDP |
Enabling Zaire to fulfill its commitments to the UNFCCC |
08/17/95 |
--- |
--- |
0.35 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |||||||
|
|
|
|
|
|
|
|
Albania |
UNDP |
Enabling Albania to prepare its first national communication |
05/15/96 |
|
|
|
Draft project document expected by Jan. 1997. |
Cambodia |
UNDP |
Enabling Activity |
11/12/96 |
|
|
|
In final review. |
Cameroon |
UNEP |
Enabling Activity |
Dec. 96 |
|
|
|
In final review |
Cape Verde |
UNDP |
Enabling Activity |
05/26/96 |
|
|
|
In final review |
|
|
|
|
|
--- |
|
|
Democratic Peoples' Republic of Korea |
UNDP |
Enabling Activity |
01/17/94 |
|
|
|
In final review. |
El Salvador |
UNDP |
Enabling Activity |
12/02/96 |
|
|
|
In final review. |
Eritrea |
UNDP |
Enabling Eritrea to prepare its first national communication |
07/05/96 |
09/04/96 |
|
|
Project document being finalized. |
Guatemala |
UNDP |
Enabling Activity |
11/18/96 |
|
|
--- |
In final review |
|
|
|
|
--- |
--- |
|
|
Georgia |
UNDP |
Enabling Georgia to fulfil its commitments to the UNFCCC |
05/24/96 |
|
|
|
Project document signature anticipated in Jan. 1997. |
Country |
Implementing Agency |
Project Title |
Date of Country Endorsement |
Date of GEF Council Approval |
Date of Project Document Signature |
GEF Allocation |
Comments |
| |||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Lesotho |
UNEP |
Enabling Activity |
06/21/96 |
|
|
|
--- |
Malawi |
UNDP |
Enabling Activity |
08/06/96 |
--- |
|
|
In final review. |
Nigeria |
UNDP |
Enabling Activity |
08/07/96 |
--- |
|
|
In final review. |
Seychelles |
UNDP |
Enabling Seychelles to prepare its first national communication |
11/16/95 |
|
|
|
Project under early stage of implemen-tation. |
Sierra Leone |
UNDP |
Enabling Sierra Leone to prepare its first national communication |
07/09/96 |
|
|
|
Project document being finalized. |
|
|
|
|
--- |
--- |
--- |
|
Uganda |
UNDP |
Enabling Uganda to prepare its first national communication |
08/22/95 |
|
|
|
Project document signature anticipated in Jan. 1997. |
|
|
|
|
--- |
--- |
--- |
|
Zimbabwe |
UNEP |
Enabling Activity |
11/04/96 |
|
|
|
In final review. |