Distr.
GENERAL
FCCC/SBI/1997/8
20 June 1997
Original: ENGLISH
SUBSIDIARY BODY FOR IMPLEMENTATION
Sixth session
Bonn, 28 July - 5 August 1997
Item 5 of the provisional agenda
Paragraphs Page
I. INTRODUCTION 1 - 4 3
II. BACKGROUND AND INSTITUTIONAL DEVELOPMENT 5 - 8 3
III. GEF OPERATIONS AND FUNDING REGARDING
CLIMATE CHANGE 9 - 21 5
A. Operational Strategy 9 - 11 5
B. GEF Funding of Activities in the Climate Change Area 12 - 18 5
C. The GEF Project Cycle 19 - 20 7
D. Project Development Support 21 7
IV. SUBMISSIONS BY PARTIES ON THEIR EXPERIENCE
WITH THE GEF 22 - 32 8
A. Governance, Responsiveness and Effectiveness 23 - 26 8
B. Recommendations 27 - 32 9
GE.97-
Paragraphs Page
V. RELEVANT INFORMATION FROM OTHER SOURCES 33 - 34 10
VI. CONCLUSIONS 35 - 43 10
GEF Monitoring and Evaluation Programme 12
1. In accordance with Article 11.4 of the Convention, at its first session, the
Conference of the Parties (COP) decided to review the financial
mechanism within four years and to take appropriate measures,
including a determination of the definitive status of the Global
Environment Facility (GEF) in the context of the Convention. In
decision 11/CP.2, in the context of guidance to the Global
Environment Facility (GEF), the COP requested the Subsidiary Body for
Implementation (SBI) at its fifth session to undertake the review
process referred to in decision 9/CP.1 and to report on the outcome
to the COP at its third session.
2. The SBI agreed to begin the review process on the basis of
guidelines which specify objectives, a methodology and criteria, and
invited Parties to submit views on their experience regarding the
financial mechanism by 15 May 1997. It requested the secretariat to
compile the submissions (FCCC/SBI/1997/MISC.3) and to prepare a
synthesis report based on the submissions received and other
information as enumerated in the guidelines, for consideration by the
Parties at the sixth session of the SBI (FCCC/SBI/1997/6, paras.18-20
and annex II). As only few submissions had been received by 15 May,
consideration was also given to additional communications which were
received by 16 June 1997.
3. The following synthesis report takes into account eight submissions from Parties, including three from Africa, two from Asia, one from Latin America, one from
North America and one by the Netherlands on behalf of the European Community and its member States. These were complemented by information provided by
25 non-Annex I Parties which had responded to a secretariat questionnaire on the status of preparation of national communications. In addition, information from other sources as enumerated in the guidelines was taken into account. Views received from an
inter-governmental organisation, the Organisation of Petroleum
Exporting Countries (OPEC) and a non-governmental organisation,
Climate Network Africa, were also reflected.
4. Given the small number of submissions by non-Annex I Parties
and the fact that the set of criteria were often not comprehensively
addressed, this synthesis report should be considered bearing these
limitations in mind. Information on the provision of support for
national communications and other GEF financing for project
activities can be interpreted with more confidence, however, as it is
more broadly-based and factual data are available.
5. The GEF had originally been established as a pilot programme to
assist in the protection of the global environment and promote,
thereby, environmentally sound and sustainable economic development.
In response to the requirements of Articles 21.3 and 11, in
particular to ensure that its membership be universal, the GEF
organised restructuring negotiations during the period April 1992
through March 1994. Through the Instrument for the Establishment of
the Restructured GEF, the following purposes were
pursued:
(a) Moving towards universal membership currently comprising 161 country Participants in the GEF;
(b) Its functioning under the guidance of the COP;
(c) The provision of financial resources on a grant or concessional basis; and
(d) Ensuring equitable and balanced representation within a
transparent system of governance comprised of an Assembly, a Council
and a Secretariat.
6. Annex D to the Instrument specified the principles of
co-operation among the Implementing Agencies (IAs), the United
Nations Development Programme (UNDP), the United Nations Environment
Programme (UNEP) and the World Bank, in particular their key roles in
the implementation of the GEF-financed projects in their respective
spheres of competence. A Scientific and Technical Advisory Panel
(STAP) was established to advise the GEF on a range of strategic
scientific and technical issues, while maintaining a limited, but
important role in the project review process.
7. In decision 12/CP.2, the COP adopted and thus brought into force the
Memorandum of Understanding between the COP and the Council of the
GEF, subsequent to the approval by the latter. The Parties to this
Memorandum agreed that its purpose is to give effect to the
respective roles and responsibilities of the COP and the GEF, and to
provide for the required interaction between them. It specifies
procedures for the determination and communication of guidance from
the COP to the Council of the GEF concerning the financial mechanism;
the conformity with COP guidance; the reconsideration of funding
decisions; the reports from the GEF to the COP; the determination of
funding necessary and available as detailed in the Annex to this
Memorandum; the cooperation between secretariats; the representation
in meetings of governing bodies; and the review and evaluation of the
financial mechanism. The Annex on the determination of funding
necessary and available for the implementation of the Convention was
approved by the Council of the GEF and is scheduled for approval by
the COP at its third session.
8. The work programme on the GEF system of monitoring and
evaluation, established by the GEF Council, includes independent
evaluation, operational, scientific and technical monitoring and
evaluation, and evaluation of strategic and cross-programme issues.
Operational monitoring and evaluation should be based on the existing
systems of the IAs while recognizing the need to harmonize the
activities of the agencies to suit the needs of the GEF. STAP should
play an important role in scientific and technical evaluation. The
monitoring and evaluation activities to be carried out during
1997-1998 are outlined in the annex to the present
document.
9. The GEF operations regarding climate change fall into the
interrelated categories which are specified below:
(a) Enabling activities, representing a basic building block of
the GEF assistance to countries (including inventories, compilation
and analysis of existing information, policy analysis, strategies,
action plans, and national communications);
(b) Projects developed under long-term operational programmes, which are in accordance with the initial three programme priorities approved by the COP, namely:
(i) Removing barriers to energy conservation and energy efficiency;
(ii) Promoting the adoption of renewable energy by removing barriers and reducing implementation costs; and
(iii) Reducing the long-term costs of low greenhouse gas emitting energy technologies.
In addition, other operational programmes to address transport and
carbon sequestration are under development.
(c) Short-term response measures in the form of high priority
projects which are in neither of the categories above, but yield
climate change benefits at low cost.
10. In addition, the Project Development Funding (PDF), instituted
at the November 1994 meeting of the GEF Council, is intended to
provide the funding, when necessary, for project development from the
initial concept stage to the final design.
11. In April 1996, the GEF Council approved its policy concerning
public involvement in projects financed by the GEF. In approving the
policy, the Council requested the GEF Secretariat to work with IAs in
preparing operational guidelines for public involvement, namely: (a)
to place emphasis on local participation and stakeholders; (b) to
consider specific local conditions; and (c) to ensure that public
involvement is consistent with provisions in the GEF
Instrument.
12. According to the GEF Quarterly Operational Report of March 1997, the GEF has provided over $US 528 million in grant financing for climate change projects and project preparation. This total excludes funds for supporting multiple focal areas projects, such as the Small and Medium-Scale Enterprise Programme and the Small Grants Programme. The estimated share of GEF resources committed to climate change projects is approximately
39 per cent (biodiversity is 35 per cent; international waters 12
per cent; ozone 8 per cent; and multi-focal areas is 6 per
cent).
13. There are currently 13 global and six regional climate change
projects in place which receive funding amounting to almost $US 100
million and over $US 26 million, respectively. These projects,
equivalent to about 20 per cent of GEF funding for climate change,
include the Photovoltaics Market Transformation Initiative, the
Renewable Energy and Energy Efficiency Fund and capacity-building
activities.
14. For a large number of non-Annex I Parties, the GEF support to date is primarily through enabling activities. The GEF resources for these projects vary in size, but are typically of the order of US$ 300,000. According to the GEF, of the approximate
103 non-Annex I Parties included in the cumulative GEF work programme, as many as
90 countries were covered in national or global/regional projects
that contain some or all the components required for the preparation
of national communications. On the other hand, technical assistance
or investment projects pertaining to one of the operational
programmes had been developed in 25 countries which have not yet
initiated the preparation of a national communication.
15. Concerning direct country projects, approximately $US 345 million were allocated within the financial mechanism, while $US 58 million went to climate change activities outside the financial mechanism. The cumulative GEF Work Programme covers a total of
77 projects through which direct support is rendered to 57 non-Annex I Parties. These include 39 enabling activities, 26 projects carried out during the pilot phase and
12 operational programme projects under the restructured
GEF.
16. About $US 15 million are dedicated to country-specific enabling activities which can be considered under expedited procedures for an immediate disbursement of 15 per cent of the total project funds, in order to allow immediate implementation. During the GEF Pilot Phase, approximately $US 180 million were allocated to 26 national programmes in
21 countries, such as for the development of renewable sources of
energy, energy efficiency measures and the development of coal-bed
methane resources. Allocations for the same purposes under the
restructured GEF totalled about $US 145 million, with 12 projects in
ten countries. Over four fifths of GEF resources for country projects
within the financial mechanism went to ten non-Annex I Parties. The
GEF financing for project preparation under PDF Block B and C grants
totals approximately US$ 5 million and covers 16 project concepts.
Other project proposals not requiring project preparation financing
are under preparation in the climate change area with the assistance
of the IAs.
17. Information is available on the GEF work programme
allocations, commitments and disbursements. Variations in the
percentage of commitments and disbursements as related to allocations
were discernable among the IAs. The higher rates of disbursement by
UNDP and UNEP in comparison to the World Bank seem to reflect the
magnitude, complexity and longevity of World Bank projects, but may
warrant further analysis in the context of the GEF Monitoring and
Evaluation programme.
18. According to the report presented by the GEF to the SBI at its
fifth session, the $US 528 million had then
leveraged an additional $US 2,730 million in project financing. The
total amount available for climate change project financing was thus
$US 3,258 million.
19. The cycle is initiated in accordance with priorities and needs expressed by
non-Annex I Parties which approach the GEF through one of its IAs.
Proposals, once endorsed by the requesting government and prior to
being submitted to the GEF Council, are subjected to a review
process, including the GEF secretariat, the IAs, the Convention
secretariat and the STAP. Once approved by the GEF Council, or, in
the case of enabling activities qualifying for expedited procedures,
once approved by the Chief Executive Officer (CEO) of the GEF, the
project document is finalized and signed by the agency and the
recipient country.
20. The analysis of information on enabling activities shows that
the average period between country endorsement of a project proposal
and its approval by the CEO on behalf of the Council is currently
about six months, as compared to 15 months before expedited
procedures were implemented by the GEF. According to information
provided by the GEF in June 1997, there are currently 37
country-endorsed projects included in the list of enabling activities
under expedited procedures. Of these projects, 26 have been approved
by the GEF and can, therefore, be considered for at least a 15 per
cent immediate disbursement. Four of these proposals have also been
signed by the relevant IA, and are being implemented. Of the
remaining 22 projects awaiting the signature by the IA, 17 had been
approved by the Council between March and May 1997 and five dated
from 1996 (FCCC/SBI/1997/MISC.4).
21. To facilitate access to resources of the GEF
and the preparation of projects, GEF project development workshops
have been organised in Africa, Asia/Pacific, Latin America/Caribbean,
Europe/Central Asia and Middle East/North Africa. Further regional
workshops have been scheduled for 1997. The GEF organised two
workshops at the fifth session of the SBI to better inform Parties
how to access GEF resources and to share experiences in implementing
climate change projects. The GEF and the Convention secretariat are
collaborating to inform Parties of available support for preparing
their national communication and provide technical
backstopping.
22. In response to the invitation by the SBI a total of eight submissions were received from Parties until 16 June 1997. Of these, six were from non-Annex I and two from
Annex I Parties. One of the latter was from the Netherlands on
behalf of the European Community and its member States. The
submissions referred, explicitly or implicitly, to the objectives
and/or criteria spelled out in the guidelines adopted by the SBI at
its fifth session. They are presented below in a summarized manner
along with a number of recommendations made by them. It should be
noted that submissions did not distinguish between the entities
constituting the GEF, namely the Secretariat, the Council and the
IAs. Neither did they specify the time-frame of the reported
experiences.
23. Certain Parties expressed a continued need for additional
information and enhanced transparency on GEF operations. Procedures
for obtaining funding and the level of funding obtainable should be
clearly indicated. This pertained to projects for the preparation of
national communications as well as to programmes and projects under
the operational strategy, like technical assistance and investment
projects. In this context it was also mentioned that progress in
transferring technology had been insufficient.
24. It was stated that GEF funding, such as allocations for the
preparation of national communications, had not been timely, was
insufficient in scope and unpredictable. This had caused delays in
meeting commitments under the Convention and, in one case, in
elaborating a national action plan. Due to problems in accessing the
required GEF support, Parties had to resort to the alternative of
approaching Annex I countries which, in some cases, had attached
conditions not always in the interest of developing countries.
Improved administrative procedures and more dynamic technical support
were needed to reduce delays in project approval and implementation
and to avoid inconsistencies and lack of responsiveness in the
preparation, consideration and operationalisation of
projects.
25. Other Parties felt that the restructuring and replenishment of
the GEF, the development of its Operational Strategy and Programmes
following the guidance of the COP as well as the agreement reached
with the Convention on its Memorandum of Understanding were all part
of a continuing process. Difficulties of developing countries in
receiving adequate financial support for the preparation of national
communications had been met by a prompt response from the GEF,
including the timely disbursement of funds through a speeding up of
procedures in the IAs. The funding process thus seemed to be
functioning more effectively. In addition, the GEF was increasingly
leveraging financial resources from both the private sector and
co-funding sources.
26. Donors, being assured by these accomplishments, had committed over $US 2 billion to the first replenishment and saw a strong basis for future replenishment. The GEF was considered to have the means for effectively transferring new and additional resources to developing country Parties to meet the agreed full costs of their obligations under Article 12.1 and the agreed full incremental costs of implementing measures that are covered by
Article 4.1 and that are agreed in accordance with Article
4.3.
B.
Recommendations
27. Increased sharing of experiences between donor and recipient countries was encouraged. It was suggested that the secretariat should arrange for experts from the GEF and its IAs to be available at the next meeting of the SBI to respond to any specific issues raised by developing country partners. It was recommended that funding through the GEF should be made available to allow Parties and Observers to exchange information and views on the implementation aspects of Specific Policies and Measures (P&M) taken by
Annex I Parties. Workshops should be convened to discuss specific
topics of the climate change agenda so that understanding would
increase and capacities be developed.
28. In addition, non-Annex I Parties responding to the
questionnaire by the secretariat on the Status of Preparation of
National Communications almost unanimously called for workshops for
exchanging information on emission factors and activity data and for
regional and subregional workshops.
29. A continuous and sustainable funding approach was recommended
in certain areas, in particular for activities related to the
preparation of national communications. It was also suggested that
projects for capacity-building should be executed by countries to
ensure that they were indeed country-driven, cost-effective and
targeted. In this context, a proposal was also made that the
Convention secretariat should be in charge of allocating funding for
the preparation of national communications so that non-Annex I
Parties could comply with their reporting commitments in
1998.
30. Regional imbalances and weaknesses should be addressed. The level of participation at the GEF Council should be reviewed and regional views should be presented at its meetings. The allocation of funding to regions was seen to be imbalanced. Focal points in the African region should be strengthened to allow for an increased flow of information.
31. The submission by the Netherlands on behalf of the European
Community and its member States recommended that the financial
mechanism should be appointed on a continuing basis, dependent on a
regular review process with a four year time-span taking into account
the conformity of the financial mechanism with the guidance of the
COP, the reports to the COP and the reports of the GEF's Monitoring
and Evaluation Programme. The review process should be structured to
monitor and influence the further improvement of the GEF in its role
as the financial mechanism of the Convention.
32. Private sector involvement and innovative financial approaches
and partnerships should be further encouraged in order to maximize
the impact of resources available from GEF, especially where
capital-intensive projects were concerned. Also, donors had
encouraged the GEF, in accordance with its mandate, to mainstream
sustainable development concerns, especially climate change
considerations, in lending practices of multi-lateral development
banks, the World Bank and other institutions. The integration of
global environment agenda into the core of programmes of IAs was
welcomed. In this context an explicit request was made to the SBI
that the necessary steps are taken to formally operationalise
paragraph 2(a) of decision 11/CP.1.
33. An intergovernmental organisation suggested that the
vulnerability of countries to climate change mitigation measures
should be one criterion of eligibility for funding by the GEF and
recommended to increase the flow of information on the availability
of its resources, including specific information on funding for
project development and preparation.
34. A non-governmental organisation noted that funds for
activities in developing countries were not adequate, predictable and
disbursed in a timely manner and that the project approval process
was lengthy. The sustainability of projects was not ensured as
resources for follow-up activities tended to be lacking. It
recommended that an inventory of resource flows to developing
countries and regions be compiled.
35. Based on the information in this initial synthesis report it
is possible to identify accomplishments as well as to indicate how
communication between the GEF, the IAs and the Parties could be
improved and where immediate remedial steps could be taken to address
general as well as country-specific problems. Additional information
emanating from the GEF's Monitoring and Evaluation exercise is
expected to be available in the fourth quarter of 1997.
36. The GEF has made considerable progress in terms of
institutional development. Its restructuring, the conclusion of a
Memorandum of Understanding between the COP and the GEF, the
establishment of a Scientific and Technical Advisory Panel, the
development of an operational strategy, the institution of expedited
procedures for the approval of enabling activities, the institution
of a Project Development Funding facility constitute significant
milestones in this regard.
37. The first replenishment of the GEF amounted to circa $US 2
billion for all focal areas. GEF funding totalling US$ 528 million in
grant financing has been provided for climate change projects and
project preparation within and outside the financial mechanism. This
financing has leveraged an additional US$ 2,730 million so that a
total of US$ 3,258 million is available for climate change projects.
In the first replenishment period, no climate change related
activities were denied funding because of the unavailability of
funds.
38. The GEF is supporting a substantial number of enabling
activities for the preparation of national communications under
Article 12. In this regard, expedited procedures have more than
halved the lead time for project approval. There still appears to be
a need to accelerate post approval procedures and implementation.
Available support for project development should promote progress in
launching and conducting the preparation of national communications
by more non-Annex I Parties.
39. Funding of mitigation projects has begun in the areas defined
in the three initial operational programmes for climate change. These
include mainly projects in the areas of renewable energy development
and energy efficiency.
40. Concerns have been expressed regarding the transparency of the
GEF decision-making process, the adequacy, predictability and timely
disbursement of funds for activities in developing country
Parties.
41. It has been recommended that efforts be made to ensure the
financial sustainability of GEF projects and to build up national and
regional capacities, including public awareness. It was suggested
that the provision of increased information on the procedures of the
GEF and the exchange of experiences among and between non-Annex I and
Annex I Parties could be helpful in this respect.
42. The Secretariat of the GEF and the IAs may wish to contact non-Annex I Parties whose submissions are contained in the compilation (FCCC/SBI/1997/MISC.3) with a view to resolving any outstanding issues.
43. A proposal has been made that the GEF should henceforth have
continuing status as the operating entity of the financial mechanism,
dependent on a regular review process.
1. Study on the GEF's Overall Performance: In the fiscal
year 1997-1998, the Senior Monitoring and Evaluation Coordinator of
the GEF is carrying out this study on strategic, institutional and
programmatic issues. It is to assess to what extent the GEF achieved
or is achieving the main objectives and guidelines of the pilot phase
and of the restructuring in 1994. The study is to inform the GEF
Assembly, planned for early 1998, the second GEF Replenishment
Process and GEF stakeholders. The study will partly build on and
complement three other GEF Monitoring and Evaluation products, which
include the Evaluation of Project lessons and the Project
Implementation Reviews (PIRs) for 1996 and 1997 encompassing overall
portfolio review, financial analysis and a summary of implementation
performance and key issues.
2. This study will be carried out during the period from April 1997 to February 1998.
A Senior Advisory Panel of six to seven members will advise the
Senior Monitoring and Evaluation Coordinator and the study team on
the operationalisation, implementation and interpretation of the
findings. Interviews with the Convention secretariat, implementing
and executing agencies, STAP, NGOs and other relevant actors will be
followed by 10 in-depth and six lesser country surveys. The draft
report is to be circulated for internal and external comments in
September 1997 and presented at a workshop during the GEF Council
meeting and NGO consultation in November 1997. A presentation is
foreseen during the COP in December 1997. The final report will be
available in English, French and Spanish.
3. This study will address overriding issues related to the GEF's performance at the strategic, institutional and programme levels and draw on the above project reviews and evaluations. Among issues to be assessed are the following: (i) the GEF's role as a catalyst in providing and leveraging resources; (ii) the effectiveness of incremental cost financing in promoting relatively large numbers of projects and simultaneously economizing on the resources of the GEF; (iii) the role of the GEF in assisting non-Annex I Parties to fulfil their commitments under the Convention, in particular the modalities of co-operation between executing agencies and national host governments, institutions and stakeholder groups;
(iv) the extent to which the GEF was helpful in promoting global environmental objectives in recipient countries; (v) the effective establishment of co-operation mechanisms and procedures for project cycle management between the GEF secretariat, IAs, STAP and the convention secretariats and other cooperation partners, including assessments of the extent to which the GEF has encouraged integration of global environmental objectives into mainstream operations of its IAs; (vi) approaches and strategies by the GEF to operationalise Convention guidance and Council decisions; (vii) examination of criteria and priorities for developing the overall portfolio, project selection and approval, the choice of viable concepts, technologies and designs, systems for learning from experience as well as demonstration and replication of promising approaches.
4. PIRs: In 1997, more than 100 projects which have been
undergoing implementation for more than one year, will be reviewed,
inter alia for their attainment of global environmental
objectives and sustainable development. The main issues scrutinized
bear relations to several criteria in the guidelines for the review
of the financial mechanism. The PIRs are to consider: (i) prospects
for sustainability and replication of project outcomes, including
global environmental benefits; (ii) ways in which the latter and
incremental costs are measurable and measured; (iii) experience with
timely provision of co-financing and government counterpart
contributions (cash and in-kind resources); (iv) experience with the
involvement of stakeholders, the private sector and NGOs; (v)
experience with regional collaboration mechanisms; (vi) assessment of
innovative approaches; and (vii) information exchange and
communication, including demonstration and replication of viable
projects.
5. Evaluation of Project Lessons: This evaluation, begun in
April 1997 and to be finalized in October 1997, is to determine the
relationship between project features and performance and is to help
implementing agencies to improve on project design. Phase I of the
evaluation will analyse 30 pilot phase projects which had been under
implementation for at least one year by 30 June 1996 and were
selected because they performed well or worse than the portfolio as a
whole. Features being monitored include the project design,
implementation and management; beneficiary/stakeholder involvement;
technological and institutional matters; country and regional
context; and monitoring and evaluation. On the basis of the analysis,
six to ten projects will receive field reviews in Phase II in order
to deepen the conclusions and to illustrate the relationship between
project characteristics and performance. Consultations with NGOs are
foreseen as well.