Uniform Reporting Format:
Activities Implemented Jointly Under the Pilot Phase
List of
Projects
A. Description of project
1) Title of project: Valga I, Boiler conversion project
2) Participants/actors:
Please fill in one table for each participant/actor. For individuals fill in as from item Function
within activity".
|
Item
|
Financier/Reporter
|
Co-reporter
|
|
Name of organisation(a):
|
Statens Energimyndighet
|
Eesti Vabariigi Keskkonnaministeerium
|
|
Name of organisation (English):
|
Swedish National Energy Administration(*
|
Ministry of the Environment of the Republic of Estonia
|
|
Department:
|
Secretariat for Climate Policy and International Co-operation
|
International Relations Department
|
|
Acronym:
|
STEM
|
EKM
|
|
Acronym (English):
|
STEM
|
MoE
|
|
Function within activity:
|
Assigned by the Swedish Government for implementation including financing arrangements.
|
Estonian Climate responsible Organisation
|
|
Street:
|
Kungsgatan 43
|
Toompuiestee 24
|
|
Post code:
|
BOX 310, S-631 04
|
10149
|
|
City:
|
Eskilstuna
|
Tallinn
|
|
Country:
|
Sweden
|
Estonia
|
|
Telephone:
|
+46 16 544 20 00
|
+372 62 62 800
|
|
Fax:
|
+46 16 544 22 64
|
+372 62 62 801
|
|
E-mail:
|
klas.tennberg@stem.se
|
|
|
WWW-URL:
|
http://www.stem.se
|
|
|
Contact person (for this activity):
|
-------------------------------------
|
-------------------------------------
|
|
Surname:
|
Knutsson
|
Kratovits
|
|
First name, middle name:
|
Gudrun
|
Andres
|
|
Job title:
|
Senior officer
|
Counsellor
|
|
Direct tel:
|
+46 16 544 20 72
|
+372 62 62 841
|
|
Direct fax:
|
+46 16 544 22 64
|
+372 62 62 845
|
|
Direct E-mail:
|
gudrun.knutsson@stem.se
|
andres@ekm.envir.ee
|
(* From 1 January, 1998, the new Swedish National Energy Administration has taken over the
responsibility for the Programme for an Environmentally Adapted Energy System in the Baltic region and
Eastern Europe (EAES Programme) from NUTEK (Swedish National Board for Industrial and Technical
Development).
|
Item
|
Borrower
|
|
Name of organisation(a):
|
AS Valga Soojus
|
|
Name of organisation (English):
|
Valga Soojus LTd
|
|
Department:
|
|
|
Acronym:
|
|
|
Acronym (English):
|
|
|
Function within activity:
|
Borrower
|
|
Street:
|
Pärna puiestee 15
|
|
Post code:
|
689206
|
|
City:
|
Valga
|
|
Country:
|
ESTONIA
|
|
Telephone:
|
+372 76 411 19
|
|
Fax:
|
+372 76 411 19
|
|
E-mail:
|
|
|
WWW-URL:
|
|
|
Contact person (for this activity):
|
-------------------------------------
|
|
Surname:
|
Piller
|
|
First name, middle name:
|
Toomas
|
|
Job title:
|
Manager
|
|
Direct tel:
|
+372 76 411 19
|
|
Direct fax:
|
+372 76 411 19
|
|
Direct E-mail:
|
|
|
Item
|
Please fill in if applicable
|
Please fill in if applicable
|
|
Name of organisation(a):
|
Võru Regionaalne Energiakeskus
|
|
|
Name of organisation (English):
|
Regional Energy Centres in Estonia
Võru Regional Energy Centre
|
ÅF International AB
|
|
Department:
|
|
|
|
Acronym:
|
Võru REK
|
|
|
Acronym (English):
|
Võru REC
|
|
|
Function within activity:
|
Local reporter
|
Technical support
|
|
Street:
|
Liiva 12C
|
Stensjögatan 3
|
|
Post code:
|
65602, Võru P.O., BOX 43
|
S-217 65
|
|
City:
|
Võru
|
MALMÖ
|
|
Country:
|
ESTONIA
|
SWEDEN
|
|
Telephone:
|
+372 78 201 45
|
+46-40-37 50 00
|
|
Fax:
|
+372 78 201 45
|
+46-40-13 03 69
|
|
E-mail:
|
|
energikonsult@ens.af.se
|
|
WWW-URL:
|
http://www.af.se/ens/english/rec
|
http://www.af.se
|
|
Contact person (for this activity):
|
-------------------------------------
|
-------------------------------------
|
|
Surname:
|
Potter
|
Mårtensson
|
|
First name, middle name:
|
Elmu
|
Roland
|
|
Job title:
|
Consultant
|
Project leader
|
|
Direct tel:
|
+372 78 201 45
|
+46-40-37 51 04
|
|
Direct fax:
|
+372 78 201 45
|
+46-40-13 03 69
|
|
Direct E-mail:
|
elmu@regen.werro.ee
|
rmn@ens.af.se
|
|
|
|
a) Organisation includes: institutions, ministries, companies, non-governmental organisations, etc.
involved in the activity, i.e. research institutes associated with the project, auditors, government agency
closely following the activity.
3) Activity:
|
Item
|
Please fill in if applicable
|
|
General description:
|
Valga town is the administrative and economic centre of Valga county, located in South Estonia. The
number of inhabitants of Valga town is approx. 16000. There are several boiler plants and district
heating networks. Most of the heat is produced in a boiler plant in the centre of the town. In this
boiler plant there are 3 oil-fired DKVR 10-13 steam boilers, Which have been converted to hot water
production in 1993. With oil firing the maximum output capacity is about 8 MW per unit. One of the
boilers has been converted to wood chip firing.
|
|
Type of project:a)
|
Fuel switching to biofuels
|
|
Location (exact, e.g. city, region,
state):
|
Valga town
Valga county
Estonia
|
|
Activity starting date:
|
10. August 1993 (Letter of Intent)
|
|
Expected activity ending date:
|
Loan expire date 31. December 2003
|
|
In operation from:
|
December 1993
|
|
Stage of activity:b)
|
Completed
|
|
Lifetime of activity if different from ending date:c)
|
Expected technical lifetime is 15 years which means that the plant is expected to be in operation
till 2009.
|
|
Technical data:d)
|
An existing mazout fired DKVR 10-13 boiler has been converted to biofuels firing through
installation a pre-furnace with fixed conical grates. Automatic fuel storage, wood chipper as well
as flue gas cleaning are included in the project.
Boiler type: DKVR 10-13 (hot water)
Boiler output: 5MW
Prefurnace: Free standing
Flue gas cleaning: Multicyclone <300 mg/Nm3
Fuel type: Wood chips, sawdust,
bark, 35-55%RH
Previous fuel : Mazout ( high-sulphur content heavy fuel oil)
Estimated heat production from the wood
fuel boiler: 25 000 MWh/year
Total production of the boiler plant: 53 000 MWh/year.
|
a) For example, using Intergovernmental Panel on Climate Change (IPCC) classification: energy efficiency;
renewable energy; fuel switching; forest preservation, restoration or reforestation; afforestation;
fugitive gas capture; industrial processes; solvents; agriculture; waste disposal or bunker fuels.
b) Circle the appropriate option.
c) Methodological work will be required to define lifetime of activities.
d) Methodological work will be required to determine for each type of activity what the minimum data
requirements are.
The life time criteria has been arranged in different groups depending on type of implemented activities.
This classification assumes a level of operation and maintenance which is normal
in western countries.
Lifetime of activity
Heat production plants (bio fuel)
|
25 years
|
New installation of all main equipment parts (fuel handling system, firing equipment and boiler)
and modernisation of secondary equipment.
|
|
15 years
|
Conversion of existing boiler but new installation fuel handling system and firing equipment.
Modernisation of secondary equipment.
|
|
10 years
|
Limited installation of new equipment (only one part of the three main parts, normally the firing
equipment). Modernisation of other equipment.
|
Heat distribution systems and sub-stations
|
25 years
|
Pre-fabricated pipes and installations using certified contractors and supervisor according to EN
norms and applicable district heating practise
|
|
15 years
|
Pre-fabricated pipes and installations without using certified contractors and supervisor
|
|
10 years
|
Modernisation of existing pipes.
|
Energy efficiency in buildings
|
25 years
|
Additional insulation roofs walls etc. with Scandinavian technology.
New installed heating systems.
|
|
15 years
|
Renovation and balancing of heating systems including thermostat valves.
|
|
10 years
|
Weather stripping windows, doors etc.
|
- if a combination of measures is done a reasonable lifetime for the project have to be calculated.
4) Cost (to the extent possible)
To the investment costs are referred the cost of the investment proper and the accumulated interest during
the grace period, generally 2 years.
The AIJ/JI cost items are the costs for:
- Technical assistance, a technical and administrative support from consultants, during the period from
definition of the project till commissioning. These costs are paid by STEM.
- Follow-up, an annual technical and economic follow-up by consultants, hired by STEM, of the operating
results of the plant with the objective to improve on its techno-economic sustainability and its climate
effect. The cost indicated is an average cost per project.
- Reporting costs – i e costs in connection with the annual reporting of the project’s
climate effects to UNFCCC. The cost indicated is an average cost per project.
- Administration –Costs for seminars, handbooks, education (capacity building) and average costs of
STEM staff per project.
- Difference in interest rates. STEM applies for its loans generally an interest rate corresponding to
6-month STIBOR (Stockholm InterBank Rate, in April 1999 3,0 %). Assuming a normal lending rate of 7 % means
that this loan is associated with a cost of 4 % in relation to normal lending rate.
Investment/instalment = the borrower’s possible own financing of the investment, followed by the
borrower’s repayment of the loan.
All costs in USD
|
Country
|
|
Valga I
|
1993
|
1994
|
1995
|
1996
|
1997
|
1998
|
|
|
|
0
|
1
|
2
|
3
|
4
|
5
|
|
Investment
|
1. Loan/debt to STEM
|
475000
|
493625
|
537000
|
469875
|
402750
|
335625
|
|
|
2. Added costs
|
0
|
18625
|
43375
|
0
|
0
|
0
|
|
|
3.Technical assistance
|
118750
|
0
|
0
|
0
|
0
|
0
|
|
AIJ/JI
|
4. Follow up
|
0
|
8375
|
8750
|
10250
|
10625
|
2750
|
|
A. Sweden
|
costs
|
5. Reporting costs
|
0
|
0
|
0
|
0
|
1063
|
0
|
|
|
6. Administration
|
40000
|
0
|
0
|
0
|
0
|
0
|
|
|
7. Difference in interest
|
4%
|
19745
|
21480
|
18795
|
16110
|
13425
|
|
|
8.Accum. costs for AIJ/JI
|
158750
|
186870
|
217100
|
246145
|
273943
|
290118
|
|
|
9.Total costs
|
633750
|
680495
|
754100
|
716020
|
676693
|
625743
|
|
Investment
|
1. Investment/Instalment
|
0
|
0
|
0
|
67125
|
67125
|
67125
|
|
2. Estonia
|
AIJ/JI
|
2. Reporting costs
|
0
|
0
|
0
|
0
|
0
|
0
|
|
costs
|
3. Other costs
|
0
|
0
|
0
|
0
|
0
|
0
|
|
|
4. Accum. costs for AIJ/JI
|
0
|
0
|
0
|
0
|
0
|
0
|
|
|
5. Total costs
|
0
|
0
|
0
|
67125
|
134250
|
201375
|
|
1 USD=
|
8
|
SEK
|
|
|
|
|
|
|
5) Mutually agreed assessment procedures:
|
Describe the procedures, including name of organisations involveda):
|
|
Ministry of the Environment of Estonia is a central Estonian authority responsible on reporting of
JI projects. This authority assigns a local institution, which is involved in to the evaluation of
the climate effects of this project and takes the main responsibility to continue measuring,
results collecting for JI-reporting.
|
a) Please ensure that detailed contact information for all organisations mentioned is reported under
section A.2 above.
B. Governmental acceptance, approval or endorsement
Bearing in mind that all activities implemented jointly under this pilot phase require prior acceptance,
approval or endorsement by the Governments of the Parties participating in these activities, which shall be
shown as follows:
(a) In the case of joint reporting, the report is submitted by the designated national authority of one
participating Party with the concurrence of all other participating Parties as evidenced by attached
letters issued by the relevant national authorities;
(b) In the case of separate reporting, the reports are submitted separately by the designated national
authority of each and every participating Party. Information will only be compiled once reports have been
received from all participating Parties.
1) For the activity:
Second report . First report was submitted 1997.
2) This report is a joint report:
- Yes, Agreement with designated national authority was signed 1997.
3) General short comment by the government(s) if applicable:
cf. Annex II, section B
C. Compatibility with and supportiveness of national economic development and socio economic and
environment priorities and strategies
|
Describe (to the extent possible) how the activity is compatible with and supportive of national
economic development and socio economic and environment priorities and strategies
|
|
The project meets the following objectives in the Estonian Energy Law and the Long-term Development
Plan for the Estonian Fuel and Energy Sector:
- efficient use of energy resources;
- to increase the share of renewable energy sources in the primary energy demand from present 8% to
13% to the year 2010;
- to reduce the environmental damage arising from fuel and energy production, transport, conversion
and distribution;
- to create the reliable energy conservation system stimulating the implementation of energy
conservation measures by consumers;
- creation and usage of energy efficient technologies, fuel/energy consuming and diagnostic
equipment.
- to develop co-operation between Baltic, Nordic and Central European countries
|
D. Benefits derived from the activities implemented jointly project
Whenever possible, quantitative information should be provided. Failing that, a qualitative description
should be given. If quantitative information becomes available, it could be submitted using the update(s).
(If the amount of quantitative information is too large, the source could be indicated.)
|
Item
|
Please fill in
|
|
Describe environmental benefits in detail:
|
Annual emission reduction:
Projected: 1998
9009 ton CO2 9963 ton CO2
138ton SO2 152 ton SO2
4 ton Nox 4 ton NOx
Lower pollution in the centre town close to the boiler plant
Improved silviculture
|
|
Do quantitative data exist for evaluation of environmental benefits?
|
Yes. Some measurements have been carried out at 1994.
|
|
Describe social/cultural benefits in detail:
|
More stable energy supply
Improved working conditions, increased motivation
More employment
Improved trade balance
|
|
Do quantitative data exist for evaluation of social benefits?
|
Yes . Several reports has been produced
SEI case study.
Involved into "Surrey -project" in 1997.
|
|
Describe economic benefits in detail:
|
Decreased fuel costs per MWh
Difference between energy price on fossil fuels and biofuels is approx. 3.5 USD/MWh
|
|
Do quantitative data exist for evaluation of economic benefits?
|
Yes. Several reports have been produced.
SEI case study.
Involved into "Surrey -project" in 1997.
|
E. Calculation of the contribution of activities implemented jointly projects that bring about real,
measurable and long-term environmental benefits related to the mitigation of climate change that would not
have occurred in the absence of such activities
1) Estimated emissions without the activity (project baseline):
Description of the baseline or reference scenario, including methodologies applied:
Present data reflect emission reductions using status quo (emissions in the period before the conversion to
renewable fuel) for the baseline case. Calculations, according to the top-down method, for emissions from
different types of projects in the baseline case are being made. The changed calculation method will result
in a change in emission reduction.
The new data will be introduced as soon as available.
2) Estimated emissions with the activity:
Description of the scenario, including methodologies applied:
Emission reductions are calculated using the IPCC Guidelines, using the Carbon Emission Factor (CEF) for
different types of fuel, using actual system efficiency. For boiler conversion, the decrease in emissions
is calculated in relation to the amount of fossil fuel replaced (status quo).
For an energy efficiency project the decrease in emissions reflects the amount of fuel that is saved
through the project. In the case that the system uses renewable fuels, the reduction is calculated
comparing the amount of fossil fuels that was used before the conversion to renewable fuels.
Below comparison is based upon that the base-line scenario represents a status quo solution.
Fill in the following tables as applicable:
Summary table: Projected emission reduction s:
|
GHG
|
Year1
=1993
|
Year2
=1994
|
Year 3
=1995
|
Year 4
=1996
|
Year 5
=1997
|
|
Planned energy production on biofuels, MWh
|
|
2800
|
25000
|
25000
|
25000
|
25000
|
|
A) Project baseline scenario
|
CO2
|
1009
|
9009
|
9009
|
9009
|
9009
|
|
CH4
|
-
|
-
|
-
|
-
|
-
|
|
N2O
|
-
|
-
|
-
|
-
|
-
|
|
other
|
-
|
-
|
-
|
-
|
-
|
|
B) Project activity scenarioa)
|
CO2
|
0
|
0
|
0
|
0
|
0
|
|
CH4
|
-
|
-
|
-
|
-
|
-
|
|
N2O
|
-
|
-
|
-
|
-
|
-
|
|
other
|
-
|
-
|
-
|
-
|
-
|
|
C) Effect ( B-A )
|
CO2
|
-1009
|
-9009
|
-9009
|
-9009
|
-9009
|
|
CH4
|
|
-
|
-
|
-
|
|
|
N2O
|
|
-
|
-
|
-
|
|
|
Other
|
|
-
|
-
|
-
|
|
|
D) Cumulative effect
|
CO2
|
-1009
|
-10018
|
-19026
|
-28035
|
-37044
|
|
CH4
|
-
|
-
|
-
|
-
|
-
|
|
N2O
|
-
|
-
|
-
|
-
|
-
|
|
Other
|
-
|
-
|
-
|
-
|
-
|
|
GHG
|
Year 8
=1998
|
...
|
...
|
...
|
Year 15
|
|
Planned energy production on biofuels, MWh
|
|
25000
|
|
|
|
25000
|
|
A) Project baseline scenario
|
CO2
|
9009
|
|
|
|
9009
|
|
CH4
|
-
|
|
|
|
-
|
|
N2O
|
-
|
|
|
|
-
|
|
other
|
-
|
|
|
|
-
|
|
B) Project activity scenarioa)
|
CO2
|
0
|
|
|
|
0
|
|
CH4
|
-
|
|
|
|
-
|
|
N2O
|
-
|
|
|
|
-
|
|
other
|
-
|
|
|
|
-
|
|
C) Effect ( B-A )
|
CO2
|
-9009
|
|
|
|
-9009
|
|
CH4
|
-
|
|
|
|
-
|
|
N2O
|
-
|
|
|
|
-
|
|
Other
|
-
|
|
|
|
-
|
|
D) Cumulative effect
|
CO2
|
-46053
|
|
|
|
-136140
|
|
CH4
|
-
|
|
|
|
-
|
|
N2O
|
-
|
|
|
|
-
|
|
Other
|
-
|
|
|
|
-
|
- Includes indirect GHG leakages
Summary table: Actual emission reductions :
|
GHG
|
Year1
=1993
|
Year2
=1994
|
Year 3
=1995
|
Year 4
=1996
|
Year 5
=1997
|
|
Factual energy production on biofuels MWh
|
|
2438
|
21204
|
17208
|
15681
|
23631
|
|
A) Project baseline scenario
|
CO2
|
879
|
7641
|
6201
|
5651
|
8515
|
|
CH4
|
-
|
-
|
-
|
-
|
-
|
|
N2O
|
-
|
-
|
-
|
-
|
-
|
|
other
|
-
|
-
|
-
|
-
|
-
|
|
B) Project activity scenarioa)
|
CO2
|
0
|
0
|
0
|
0
|
0
|
|
CH4
|
-
|
-
|
-
|
-
|
-
|
|
N2O
|
-
|
-
|
-
|
-
|
-
|
|
other
|
-
|
-
|
-
|
-
|
-
|
|
C) Effect ( B-A )
|
CO2
|
-879
|
-7641
|
-6201
|
-5651
|
-8515
|
|
CH4
|
|
-
|
-
|
-
|
|
|
N2O
|
|
-
|
-
|
-
|
|
|
Other
|
|
-
|
-
|
-
|
|
|
D) Cumulative effect
|
CO2
|
-879
|
-8519
|
-14720
|
-20371
|
-28886
|
|
CH4
|
-
|
-
|
-
|
-
|
-
|
|
N2O
|
-
|
-
|
-
|
-
|
-
|
|
Other
|
-
|
-
|
-
|
-
|
-
|
|
GHG
|
Year 6
=1998
|
...
|
...
|
...
|
Year 5
|
|
Factual energy pro-duc-tion on biofuels MWh
|
|
27649
|
|
|
|
27649
|
|
A) Project baseline scenario
|
CO2
|
9963
|
|
|
|
8515
|
|
CH4
|
-
|
|
|
|
-
|
|
N2O
|
-
|
|
|
|
-
|
|
other
|
-
|
|
|
|
-
|
|
B) Project activity scenarioa)
|
CO2
|
0
|
|
|
|
0
|
|
CH4
|
-
|
|
|
|
-
|
|
N2O
|
-
|
|
|
|
-
|
|
other
|
-
|
|
|
|
-
|
|
C) Effect ( B-A )
|
CO2
|
-9963
|
|
|
|
-9963
|
|
CH4
|
-
|
|
|
|
-
|
|
N2O
|
-
|
|
|
|
-
|
|
Other
|
-
|
|
|
|
-
|
|
D) Cumulative effect
|
CO2
|
-38850
|
|
|
|
-138483
|
|
CH4
|
-
|
|
|
|
-
|
|
N2O
|
-
|
|
|
|
-
|
|
Other
|
-
|
|
|
|
-
|
a) Includes indirect GHG leakages.
F. Additionality to financial obligations of Parties included in Annex II to the Convention within the
framework of the financial mechanism as well as to current official development assistance flows
Please indicate all sources of project funding.
|
Category of funding
(For each source one line)
|
Amount
(US dollars)
|
|
Loan from NUTEK
|
506666 USD
|
|
Grant from NUTEK for technical assistants
|
126691 USD
|
1 USD = 7.50 SEK
G. Contribution to capacity building, transfer of environmentally sound technologies and know-how to
other Parties, particularly developing country Parties, to enable them to implement the provisions of the
Convention. In this process, the developed country Parties shall support the development and enhancement of
endogenous capacities and technologies of developing country Parties
|
Transfer of environmentally sound technologies and know-how
|
Describe briefly
|
|
Schematically, the transfer of knowledge involves the following activities over time:
i) Technology transfer through NUTEKs technical specialist during the implementation of the
project.
ii) Technology transfer through co-operation between foreign supplier and local partner
iii) Conferences, seminars, documentation and training.
iv) Stimulate "net-working" for the exchange of experience between plant owners with
similar problems, e g "bio-clubs"
|
Technology transfer has taken place through:
- STEM technical specialist support to the local project leader and municipality;
Knowledge in negotiations to foreign companies;
Knowledge in managing and planning of projects;
Transferring of environmental issues to the local parties;
Transferring of knowledge in operation and maintenance issue;
Operation and maintenance software was introduced to the plant-owners.
- Personal from boiler plant has been invited to different seminars and work-shops and
several presentations about company experience have made, documentation for training has been
handed over.
There were arranged seminars through close cooperation between STEM and Estonian partners:
- Environmentally Friendly Energy Systems in the Baltic Region and Eastern Europe - seminar in
Tallinn , 14-15 Aprill, 1994;
- Environmentally Friendly Energy Systems in the Baltic Region and Eastern Europe - seminar and
workshops in Tartu , 25 November, 1994 (prepared information by topics in Estonian over than 150
pages);
- EAES Programme District Heating Day in Vändra, 27 July, 1995;
- Environmentally Adapted Local Energy Systems - seminar and presentation of translated into
Estonian booklet "Environmentally Adapted Local Energy Planning" in Rakvere, 11 November,
1998 and in Tartu, 12 November, 1998.
iv)Activities have been supported by STEM to establish Estonian Biofuels Association: meetings
representatives of plant owners and consultants were arranged in Haabneeme, Valga, Võru,
Tartu, Pärnu and Viljandi.
Boiler plant has been visited by specialist of other boilerplants, the staff has an exchange of
experience with other boilerplants and was active in "bio-club". Estonian Biofuels
Association is established in 1998 ( mainly by "bio-club" and local experts) and the
company is a member.
|
Endogenous capacity supported or enhanced:
|
Endogenous capacity
Name of organisation1)
|
Development (DEV) /
enhancement (ENH)
|
Describe briefly
|
|
Valga Heating Co
|
(DEV)
|
The boiler plant has got an experience to handle biofuel firing equipment
|
1) Please ensure that detailed contact information for all organisations listed is reported under section
A.2 above .
H. Additional comments, if any, including any practical experience gained or technical difficulties,
effects, impacts or other obstacles encountered
Fill in as appropriate:
1) Any practical experience gained:
Good training and experience of the staff is necessary to operate biofuel boiler at full capacity. The
motivation of the staff to learn is very important to get good results.
The company has in site logs chipping practice. During the last year the chipper has not been in operation,
logs price is arised.
The wood chips storage building height must be bigger to not prevent unloading the trucks.
The operation of the prefurnace with fixed grates needs good trained and skilled staff.
2) Technical difficulties:
3) Effects encountered:
Execution of the follow up and monitoring activities to get feedback to the programme and for evaluation of
the results of the different measures.
Consulting support from both Swedish and Estonian side, also after commissioning.
4) Impacts encountered:
5) Other obstacles encountered: Ash handling has caused stops. Improvements have been done and a
higher efficiency is expected.
The plant has had a management problems because the management has been changed several times. It has taken
time to develop normal operational practices. There have been heat production brakes resulted mainly of
general operational problems.
Lack of a strong national focal point to support and promote biomass energy activities.
6) Other:
From 1998 the wood-fuel is purchased according to the produced heat from converted boiler.
No subsidies to renewables, taxation policy is not in support of biofuels use.