Uniform Reporting Format:
Activities Implemented Jointly Under the Pilot Phase
Annex I
List of
Projects
A. Description of project
1) Title of project:
Baisiogala Boiler Conversion
2) Participants/actors:
|
Item
|
Financier/Reporter
|
Co-reporter
|
|
Name of organisation(a):
|
Statens energimyndighet
|
Aplinkos Ministerija
|
|
Name of organisation (English):
|
Swedish National Energy Administration
|
Ministry of Environment
|
|
Department:
|
Secretariat for Climate Policy and International Co-operation
|
Environmental Quality Department
|
|
Acronym:
|
STEM
|
AM
|
|
Acronym (English):
|
STEM
|
MoE
|
|
Function within activity:
|
Assigned by the Swedish Government for implementation including financing arrangements.
|
Assigned by the Lithuanian Government for activities implemented jointly
|
|
Street:
|
Kungsgatan 43
|
Jakšto 4
|
|
Post code:
|
BOX 310, S-631 04
|
LT-2600
|
|
City:
|
Eskilstuna
|
Vilnius
|
|
Country:
|
Sweden
|
Lithuania
|
|
Telephone:
|
+46-16 544 20 00
|
+370-2 61 90 49
|
|
Fax:
|
+46-16 544 22 64
|
+370-2-22 08 47
|
|
E-mail:
|
klas.tennberg@stem.se
|
atm@nt.gamta.lt
|
|
WWW-URL:
|
http://www.stem.se
|
http://www.gamta.lt
|
|
Contact person (for this activity):
|
-------------------------------------
|
-------------------------------------
|
|
Surname:
|
Knutsson
|
Bilkis
|
|
First name, middle name:
|
Gudrun
|
Mindaugas
|
|
Job title:
|
Head of Section, Climate Investment Programme
|
Director of Environmental Quality Dept.
|
|
Direct tel:
|
+46-16 544 20 72
|
+370-2-61 90 49
|
|
Direct fax:
|
+46-16 544 22 64
|
+370-2-22 08 47
|
|
Direct E-mail:
|
gudrun.knutsson@stem.se
|
atm@nt.gamta.lt
|
|
Borrower
|
|
Name of organisation(a):
|
UAB "Pakirsinio Komunalinis Ukis"
|
|
Name of organisation (English):
|
Joint Stock Company "Pakirsinio Komunalinis Ukis"
|
|
Department:
|
|
|
Acronym:
|
|
|
Acronym (English):
|
|
|
Function within activity:
|
Borrower
|
|
Street:
|
-
|
|
Post code:
|
5120
|
|
City:
|
Radviliskio district, Pakirsinio village
|
|
Country:
|
Lithuania
|
|
Telephone:
|
+370 92 44 584
|
|
Fax:
|
-
|
|
E-mail:
|
-
|
|
WWW-URL:
|
-
|
|
Contact person (for this activity):
|
|
|
Surname:
|
VALBA
|
|
First name, middle name:
|
EDMUNDAS
|
|
Job title:
|
Director
|
|
Direct tel:
|
+370 92 44 584
|
|
Mobile tel:
|
+370 85 27 778
|
|
Direct fax:
|
-
|
|
Direct E-mail:
|
-
|
|
Item
|
Please fill in if applicable
|
Please fill in if applicable
|
|
Name of organization(a):
|
Lietuvos energetikos institutes
|
ÅF Energikonsult Syd AB
|
|
Name of organization (English):
|
Lithuanian Energy Institute
|
|
|
Department:
|
Heat-Equipment Research and Testing Laboratory
|
ÅF - International AB
|
|
Acronym:
|
LEI
|
ÅFE
|
|
Acronym (English):
|
LEI
|
AFE
|
|
Function within activity:
|
Local reporter
Responsible for the measuring and collecting results for EAES-reporting.
|
Technical support
|
|
Street:
|
Breslaujos 3
|
Stensjögatan 3
|
|
Post code:
|
LT 3035
|
S-217 65
|
|
City:
|
Kaunas
|
MALMÖ
|
|
Country:
|
Lithuania
|
SWEDEN
|
|
Telephone:
|
+ 370 (7) 45 34 95, 40 18 63
|
+46-40-37 50 00
|
|
Fax:
|
+ 370 (7) 35 12 71
|
+46-40-13 03 69
|
|
E-mail:
|
testlab@isag.lei.lt
|
|
|
WWW-URL:
|
http://www.lei.lt
|
http://www.af.se
|
|
Contact person (for this activity):
|
-------------------------------------
|
-------------------------------------
|
|
Surname:
|
Pedisius
|
Mårtensson
|
|
First name, middle name:
|
Nerijus
|
Roland
|
|
Job title:
|
Senior Research Associate
|
project leader
|
|
Direct tel:
|
+ 370 (7) 40 18 64
|
+46-40-37 51 04
|
|
Direct fax:
|
+ 370 (7) 35 12 71
|
+46-40-13 03 69
|
|
Direct E-mail:
|
nerijus@isag.lei.lt
|
rmn@ens.af.se
|
|
|
|
a) Organisation includes: institutions, ministries, companies, non-governmental organisations, etc.
involved in the activity, i.e. research institutes associated with the project, auditors, government agency
closely following the activity.
3) Activity:
|
Item
|
Please fill in if applicable
|
|
General description:
|
Pakirsinis is a small village in the middle of Lithuania. In boiler plant with an annual production
about 12 000 MWh, there were two coal-fired DKVR 4-13 boilers.
|
|
Type of project:a)
|
Fuel switching to renewable
|
|
Location (exact, e.g. city, region, state):
|
Pakirsinis
Radviliskis Region
LITHUANIA
|
|
Activity starting date:
|
1995-03-22(Letter of Intent)
|
|
In operation from:
|
December 1995
|
|
Expected activity ending date:
|
30. September 2005
|
|
Stage of activity:b)
|
Complete
|
|
Lifetime of activity if different from ending date:c)
|
Expected technical lifetime is 15 years which means that the plant is expected to be in operation
till 2009.
|
|
Technical data:d)
|
Conversion of a DKVR 4-13 coal-fired boiler. The output power after conversion is estimated at 3 MW
and an annual heat production of around 12 000 MWh
|
a) For example, using Intergovernmental Panel on Climate Change (IPCC) classification: energy efficiency;
renewable energy; fuel switching; forest preservation, restoration or reforestation; afforestation;
fugitive gas capture; industrial processes; solvents; agriculture; waste disposal or bunker fuels.
b) Circle the appropriate option.
c) Methodological work will be required to define lifetime of activities.
d) Methodological work will be required to determine for each type of activity what the minimum data
requirements are.
Lifetime of activity
Heat production plants (bio fuel)
|
25 years
|
New installation of all main equipment parts (fuel handling system, firing equipment and boiler)
and modernisation of secondary equipment.
|
|
15 years
|
Conversion of existing boiler but new installation fuel handling system and firing equipment.
Modernisation of secondary equipment.
|
|
10 years
|
Limited installation of new equipment (only one part of the three main parts, normally the firing
equipment). Modernisation of other equipment.
|
Heat distribution systems and sub-stations
|
25 years
|
Pre-fabricated pipes and installations using certified contractors and supervisor according to EN
norms and applicable district heating practise
|
|
15 years
|
Pre-fabricated pipes and installations without using certified contractors and supervisor
|
|
10 years
|
Modernisation of existing pipes.
|
Energy efficiency in buildings
|
25 years
|
Additional insulation roofs walls etc. with Scandinavian technology.
New installed heating systems.
|
|
15 years
|
Renovation and balancing of heating systems including thermostat valves.
|
|
10 years
|
Weather stripping windows, doors etc.
|
- If a combination of measures is done a reasonable lifetime for the project have to be calculated.
4) Plant cost (to the extent possible):
To the investment costs are referred the cost of the investment proper and the accumulated interest during
the grace period, generally 2 years.
The AIJ/JI cost items are the costs for:
- Technical assistance, a technical and administrative support from consultants, during the period from
definition of the project till commissioning. These costs are paid by STEM.
- Follow-up, an annual technical and economic follow-up by consultants, hired by STEM, of the operating
results of the plant with the objective to improve on its techno-economic sustainability and its climate
effect. The cost indicated is an average cost per project.
- Reporting costs – i.e. costs in connection with the annual reporting of the project’s
climate effects to UNFCCC. The cost indicated is an average cost per project.
- Administration – average costs of STEM staff per project.
- Difference in interest rates. STEM applies for its loans generally an interest rate corresponding to
6-month STIBOR (Stockholm InterBank Rate, in April 1999 3,0 %). Assuming a normal lending rate of 7 % means
that this loan is associated with a cost of 4 % in relation to normal lending rate.
Investment/instalment = the borrower’s possible own financing of the investment, followed by the
borrower’s repayment of the loan.
All costs in USD
|
Country
|
|
Baisogala
|
1995
|
1996
|
1997
|
1998
|
1999
|
2000
|
|
|
|
0
|
1
|
2
|
3
|
4
|
5
|
|
Investment
|
|
|
|
|
|
|
|