THE PROJECT OF JOINT IMPLEMENTATION

"Construction of the Steam-Gas Electrical Power Station "Kuban " (Novokubansky District of Krasnodarsky region, Russian Federation) and Local Heating Systems in Krasnodarsky Region"
 
Krasnodar, RUSSIA 10 January 2000

Customer: OOO "Yougstroyinvest Ltd." - Russia

General Director V.I. Chuiko

Investor: ANKORS Management GmbH - Germany

President Valdemar Reis

The business-plan

executor of JI Joint-Stock Company of Open Type

Project "YougORGRES" - Russia

General Director S.V.Inkov

Vice-Principal Engineer V.D.Chkira

The responsible executor O.V.Yachin

Customer: "Yougstroyinvest " Ltd. Company – Russian Federation

Organisation

The name of the organisation

"Yougstroyinvest" INN 8903017634

The name of the organisation (english)

Region

Yamalo-Nenezky autonomous district

Nadim, Nadimsky region

The direction of the activity

Building

Street

1. Zvereva 451

2. Krasnodarsky av. 7

Town

1. Nadim

2. Gulkevichi

Region

1. Yamalo-Nenezky

2. Krasnodarsky

Post Index

1. 626711

2. 352156

Country

Russian Federation

Phones

1. (34595) 67-969

2. (86160) 2-2960

Fax

1. (34595) 67-969

2. (86160) 2-29-60

The responsible executor

Surname

Chuiko

First name, Patronymic

Valery Ivanovich

Post

General director

Phone

(902) 696-28-50.

Fax

(86160) 2-29-60

E-mail

Executor

Surname

Maruchenko

First name, Patronymic

Natalia Nikolaevna

Post

Director

Phone

(902) 696-28-50

Fax

(86160) 2-29-60

E-mail

Investor: ANKORS Management GmbH - Germany

Organisation

The name of the organisation

ANKORS Management GmbH

The name of the organisation (english)

Ancors Management ¹ HRB 29242

Region

The direction of the activity

Management

Street

Mainhainer str. 203

Town

Bad Kreuznach

Region

Rollan Falz

Post Index

55543

Country

Germany

Phone

(491) 1703519588

Fax

(491) 6701960675

The responsible executor

Surname

Reis

First name, Patronymic

Valdemar

Post

President

Phone

(491) 73519588

Fax

E-mail

Ancors@gmx.de

Executor

Surname

Chelenberg

First name, Patronymic

Andreas

Post

General Director

Phone

(491) 1703519588

Fax

(491) 6701960675

E-mail

Ancors@gmx.de

1. The Brief Description of the Project

According to the classification of the Inter-Governmental Panel on Climate Change the project "Construction of the Steam-Gas Electrical Power Station "Kuban" (Novokubansky district of Krasnodarsky region, Russian Federation) and of the Local Heating Systems in Krasnodarsky region" (Project) is directed to the decrease of anthropogenic impact on climate which is exhibited in reduction of green-house gases emission as a result of the increase of the efficiency of energy resources use.

The decrease of emissions are achieved in the way of reconstruction to the present used Municipal heating systems installing heating pumps to supply with heat houses, industrial spaces and constructions of Krasnodarsky region foreseen by the Project.

Taking into account the deficit in supplying with electricity Krasnodarsky region and with a purpose to provide with the electrical energy the designed local heating systems it’s planned to build up a steam-gas electrical power station called "Kuban" in Novokubansk city of Krasnodarsky region with the projected capacity 900 Mw in the framework of the Project realization.

The use of steam-gas cycle which has a higher rate of efficiency gives a possibility to increase the effectiveness of use the fuel energy simultaneously reducing green-house gases emission per unit of produced electrical energy.

Decisions stipulated by the Project allow refusing from the share of exploited municipal heating boiler plants network and heating systems to reduce losses existing in them, and in an outcome to increase effective use of souses of energy, and decrease green-house gases emission.

The reduction of number of staff servicing municipal heating system and boiler-houses, is compensated by necessity of staff for periodic maintenance service of heating pumps for designing local networks.

The climatic efficiency of the Project can be reached in combination of two modern technological decisions on this Project. It permits to reduce considerably green-house gases emissions under the condition of provision the customers in Krasnodarsky region with heat and electrical energy.

The volume of finance of the Project is $ 1 620 000 000:

The schedule of financing (2000 - 2003 years)
2000 year $ 162.0 million
2001 year $ 618.0 million
2002 year $ 470.0 million
2003 year $ 370.0 million
The schedule of introduction of potencies
First turn (300 Mw) 2002 year
Second turn (300 Mw) 2003 year
Third turn (300 Mw) 2004 year

2. The calculation of green-house gases emission of boiler-houses of Krasnodar region before realization of the Project (in ÑÎ2 equivalent)

Characteristics of sources

Factual

index

Expenditure of equivalent fuel,

thousand/year

Volume of green-house gases emission (in ÑÎ2 equivalent), million tons/year

Municipal boiler-houses and independent (autonomous) heating systems incinerated organic fuel of Krasnodarsky region.

1878

5 100 000

12.240

Total

1878

5 100 000

12.240

3. The calculation of green-house gases emission of the Project "Construction of the Steam-Gas Electrical Power Station “Kuban” (Novokubansky District of Krasnodarsky region, Russian Federation) and Local Heating Systems in Krasnodarsky Region” (in ÑÎ2 equivalent)

Characteristics of sources

Real indexes

in Mw

Expenditure of standard fuel in

thousand tons per year

Volume of greenhouse gases emission (in ÑÎ2 equivalent ) in million tons per year

Municipal boiler-houses and independent (autonomous) heating systems incinerated organic fuel of Krasnodarsky region.

1008

2 700 000

6.570

The Steam-Gas Electrical Power Station "Kuban "

900 Ìw

940 000

2.256

Total:

3 968 000

9.540

4. The reduction of greenhouse gases emission in result of realization of the Joint Implementation Project "Construction of the Steam-Gas Electrical Power Station “Kuban ” (Novokubansky District of Krasnodarsky region, Russian Federation) and Local Heating Systems in Krasnodarsky Region” (in ÑÎ2 equivalent)

(in ÑÎ2 equivalent)

Greenhouse gases emission 2003. 2004 ,,,,,,,,,,,,,,,,,, 2011 2012

Before the realization of the Project

Municipal boiler-houses and independent (autonomous) heating systems incinerated organic fuel of Krasnodarsky region

12.24

12.24

12.24

12.24

12.24

After the realization of the Project

Municipal boiler-houses and independent (autonomous) heating systems incinerated organic fuel of Krasnodarsky region

The Steam-Gas Electrical Power Station "Kuban"

6.570

2.970

6.570

2.970

6.570

2.970

6.570

2.970

6.570

2.970

Effect of reduction of greenhouse gases according to the Project

-2.700

-2.700

-2.700

-2.700

-2.700

5. Conclusion

The positive effect of the Project is concluded in the reduction of greenhouse gases emission resulting from the exploitation at the territory of Krasnodarsky region of municipal boiler-houses and independent (autonomous) heating systems incinerated organic fuel.

Under the conditions of putting into action of solutions proposed in the Project climatic effect in general over Krasnodarsky region predicted according to the calculations over the Project will reach reduction of greenhouse gases emission not less than 2 700 000.0 (two millions seven hundreds thousand tons) tons per year (in ÑÎ2equivalent).

In the time of elaboration of the Project documentation in according the content of the Project and its realization the climatic efficiency is going to increase, and finally it will be assessed under the procedure of Project certification.

6. Location of Steam-Gas Electrical Power Station "Kuban"

Image

Image

THE PROJECT OF JOINT IMPLEMENTATION ENERGY SAVING TECHNOLOGY INTRODUCTION

IN KRASNODAR REGION

TOPHEAT GAS EMISSION REDUCTION

IN KRASNODAR REGION

STEAM-TO-GAS POWER GENERATING PLANT "KUBAN" FIXED CAPACITY 900 Ìw and LOCAL HEAT SUPPLY STATIONS IN KRASNODAR REGION PROJECT COSTS 1.620 bln. USD

THE BEGINNING OF THE DESIGNING

AND CONSTRUCTION II QUARTER 2000

PUTTING INTO OPERATION 1 TURN – 2002

2 TURN – 2003

3 TURN – 2004